Insight
The Gateway regime imposed by the Building Safety Act 2022 on higher-risk buildings (“HRBs”, namely those over 7 storeys or 18 meters in height that contain or will contain at least 2 residential units) has come under fresh scrutiny recently after concerns were mounting over the Building Safety Regulator (“BSR”)’s resourcing problems disrupting development and remediation works throughout the industry.
In brief, the regime (in force from October 2023) is as follows:
For each Gateway, the BSR relies on a variety of external support such as a multi-disciplinary team at Gateway 2. The co-ordination of these resources is for the BSR to arrange, which has been cited as where the current problem lies.
The original assumptions as to the timeframes for approvals (12 weeks at Gateway 2 for new HRBs and 8 weeks for existing buildings) have been shown to be extremely inaccurate. Andrew Moore of the BSR reported 22 weeks for the process in February, and the situation has not improved – accepting the original caveat for complicated works, the extended delays are now resulting in timescales of 25-40 weeks for approvals at Gateway 2 and there are concerns that delays will begin to be seen at Gateway 3 as well.
The BSR responded to this in May 2025 citing that incomplete or insufficient applications were also a cause, and promised to take a “firmer approach” – rejecting applications outright without effectively wasting time on applications that will ultimately be rejected due to lack of content. This was followed on 23 June 2025 by the House of Lords launching a committee which issued a call for evidence from the industry on the performance of the BSR.
Few construction projects are planned with the contingency of nearly a year’s wait for approvals, and the development process cannot accommodate such a pause due to several important factors such as pricing, lease/funding requirements, planning permission and housing need – all of which could be seriously compromised by the delays.
On the practical side, the onus is on developers, Principal Designers and Principal Contractors who make the applications to ensure that they are made in such a way that when the BSR considers the application, it is satisfied as to its compliance without drawing out the process. Those responsible need to actually set out what they consider the applicable regulations to be (referencing not just Building Regulations but also the relevant codes and guidance that may apply), and to pick apart the design to illustrate where it meets these requirements throughout.
Those planning HRB work are encouraged to obtain outside consultancy assistance for getting applications right in the first place, issued at the right time and that the necessary information gathering is conducted well in advance of submission.
We can look to the legal documents for some room for manoeuvre. Some suggestions are as follows:
Even where these considerations and allocation of risks have been fully considered at the outset of the project, setbacks arising from the BSR’s delays will still create a risk for the project, given the inherent complexities and uncertainties linked to many delay related claims.
This may be particularly so where BSR related delays occur concurrently with other unconnected delay events, and/or are caused or exacerbated by reason of earlier delay events. Whether or not the contract terms provide that BSR delays give the contractor an entitlement to time and/or money, the interplay of that delay event to any other delays affecting the project may still increase the chances of the parties ending up in a dispute. Full record keeping and proactive management of delay events will therefore be important to ensure that disputes can be avoided or resolved favourably at an early stage.
BSR delays may also cause an employer to give instructions to reduce the scope of work and/or accelerate performance of the remainder of the works. Again, as both can give rise to complex and highly fact sensitive valuation disputes, it will be imperative to ensure that contractual and valuation processes are followed fully and promptly, and early advice is taken in relation to any potential disputes.
Ultimately, a degree of pragmatism will be required, not only to minimise the time and costs that may be incurred if matters progress to a formal dispute, but also in recognition the risk of heavy “risk shifting” causing insolvency either at main contractor level or lower down the supply chain, including by reason of cash flow difficulties caused by what may be significant delays to the project.
While steps are being taken to attempt to reduce delays, for the meantime, developers need to ensure they work with their legal partners to build in as much flexibility as possible to mitigate both the prospect of delays and the potential impact of them.
If you have any questions about the topics raised in this article, our BSA team can help. We have expertise in helping organisations navigate the complexities of the building safety regime. We take a joined up approach, that draws on expertise from across our Construction, Real Estate, Real Estate Finance and Real Estate Disputes departments.